Two boardwalks near Green Level Church Road will be re-decked. This will require closure of these areas while work is occurring. Signage will be installed notifying all users of the closure. A recommended detour will involve usage of Green Level West Road to maintain connection between American Tobacco Trail and the continuation of White Oak Greenway. For detour, see image below.

Detour around White Oak Greenway re-decking project

Project Schedule

Work will typically occur on weekdays beginning each Monday morning and reopening the following Friday in order to be accessible on weekends. No work will occur on Thanksgiving (Nov 26 & 27), or December 24 thru January 3. 

  • Work is planned to start October 26, 2020.
  • Work is planned to be complete in Spring 2021.
  • STATUS NOVEMBER 23, 2020 - APPROXIMATELY 40% OF THE PROJECT IS COMPLETE

 Work and schedule is weather dependent and may change.

 IMG_20200717_070104070

Background

We annually get 1/3 of our pedestrian structures inspected by a third party consultant. However, for the White Oak Creek Greenway boardwalks, several years ago we started to notice regular deterioration and changed these structures to annual inspections to try and keep up with regular maintenance. Based on the most recent inspection it is time to re-deck the structure completely and make minor needed structural repairs. 

Contact

311 or Paul Kuhn, PLA, (919) 469-4360, Paul.Kuhn@TownofCary.org